Final Inspection Signature

The punch card is closed.  Check out the scan of the punch card below.  I circled the important part in red.

PunchCard-Web

We broke ground in December, 2005.  Our first inspection signature (for new garage footings) was on 1/13/2006.  It has been a long road.  We still have a ways to go (painting, countertops, stair carpet, etc), but as far as the city is concerned we are good enough.

Recent Work

My goal is to get the final inspection signed off before the end of 2009.  A couple of weeks ago, the Carpinteria inspector, Jeff, came by to talk about what needed to be done to get the final sign off.  He had a list of 5 things that he needed to see completed before the final inspection.

We worked on the list and we have completed all of the tough tasks.  The main 3 things that needed to be done were:

  • Have a solid divider between the mechanical space under the stairs and the conditioned, living space.  This was completed by using one of the old doors that we removed.  This door is temporary as we have plans to build a hinged book case in this space.  But for now, the door should satisfy the requirements.
    IMG_5675-400
  • Have a working kitchen sink.  We have the sink dropped in.  I just have to hook up the water and the drain.  Toby picked out a Franke Composite Granite single bowl sink.  It is very large.   Below is a picture from the Lowe’s website.
    039487141937-400
    No counter tops, but the sink is in.

    IMG_5674-400

  • Have a stair rail for the first flight of stairs.  I would have loved to not have a stair rail, but the building code in California requires one.  Pop and Kevin spent a long time making this just right.  It is not painted, but it is solid.
    IMG_5676-400

I will do the final hookups to the kitchen sink on Saturday and then call the inspector, hopefully for the last time.

A Distressing Picture

Can you tell what this picture is?

IMG00115-20091205-1403-400

This is what I saw the morning that I left for some computer training in Las Vegas, NV.  With no time to do anything about it, I just took the picture.

When I got home, the image hadn’t changed, and I knew I had a problem.  The picture is my foundation wall and the dark spot is water on the concrete.  The white lines show that the water has been running for a while.  Since there are no leaks inside the house, this means that the leak is either under the house, or worse, in the wall.

I went under the house and found the leak.  It was easy to find due to the puddle of mud.  I counted a drop every 4 seconds.  I wiggled the pipe and the water started to spray out.  No more slow leak.

Poppa and I opened up the wall, but the leak was actually in between the floor and the baseboard.  I had driven a 16 penny nail straight though the middle of the copper pipe, probably back in July, before the drywalling.  We were able to cut out the leaking section and I got to sweat the copper under the house (my favorite! <end sarcasm>).  At least no hot solder dripped on my arms this time.

Now that there is no leak, there is no dark spot on the foundation anymore.  Woohoo!